Norfolk Southern has begun rail replacement ahead of schedule in Goshen. Closures will continue working West to East and North to South. Norfolk-Southern’s crews anticipate re-opening each crossing the same day it is closed. See the table below for an estimated schedule of closures for this week.
Railroad Crossing Currently Closed | Railroad Crossing Closed as Early as this Afternoon or Tuesday, 5/7 | Railroad Crossing Closed as Early as Tuesday, 5/7 |
Peddlers Village Rd | Plymouth Ave | College Ave |
Greene Rd | Jackson St | Kercher Rd |
Purl St | Burdick St | |
Reynolds St | New York St |
Work will continue in approxitmately one month for NS crews to finish paving.
Crossings at College Ave., Plymouth Ave., Reynolds Street, Purl Street, Greene Road, and Peddlers Village should be open by the end of the day Monday, May 6. Crossings between College Avenue and Plymouth may be closed until Tuesday, May 7. If possible try to utilize Kercher Road and Lincolnway East / US 33 for travel Monday evening but expect delays on Kercher Road Tuesday. Madison Ave will also be open Monday and Tuesday as an alternative route.
The city will provide ongoing updates as they become available.